Data centers US utilities have signed would emit as much CO2 as Poland
US utilities report signed agreements to serve 153 GW of new large load, mostly data centers, more than 9 times the capacity of the 403 largest US data centers a Harvard-led study counted in 2024-25. Modelled the way that study modelled those 403, that load would use 776 TWh a year, 17% of US electricity and more than the Texas and California grids use together, and emit 272 million metric tons of CO2 on today's grid, about as much as Poland. The 60 AI campuses running today already have 16 GW of power and would emit 28.5 Mt, by Epoch AI estimates.
CO2 a year from signed data center load, the largest data centers of 2024-25, and countries
Million metric tons of CO2. Data centers at 58% of capacity on today's grid; countries' fossil CO2 in 2024.
United Kingdom318 Mt
Poland279 Mt
Signed data center load272 Mt
France261 Mt
Spain209 Mt
60 AI campuses running today28.5 Mt
Denmark27.0 Mt
Bolivia25.8 Mt
403 largest data centers, 2024-2525.7 Mt
CO2 a year from each utility's signed load
Million metric tons of CO2, with the signed load in GW. AEP's 45 GW in Texas alone would emit 76.1 Mt.
AEP in Texas (45 GW)76.1 Mt
Georgia Power (16 GW)30.3 Mt
AEP in PJM (18 GW)29.7 Mt
Dominion (12 GW)19.8 Mt
PPL Electric (11 GW)18.2 Mt
APS (4.5 GW)15.0 Mt
AEP in SPP (6.0 GW)12.1 Mt
FirstEnergy (6.4 GW)10.6 Mt
NV Energy (6.0 GW)9.7 Mt
Duke Energy (7.8 GW)8.7 Mt
Alliant (3.4 GW)7.7 Mt
Ameren Missouri (2.8 GW)6.3 Mt
Evergy (3.0 GW)6.0 Mt
LG&E and KU (1.3 GW)5.7 Mt
DTE (2.4 GW)5.4 Mt
Xcel Energy (2.0 GW)4.5 Mt
PG&E (4.5 GW)3.8 Mt
Consumers Energy (1.0 GW)2.3 Mt
CO2 per kWh on the grids where the load is signed
Average CO2 per kWh generated, 2023. A GW signed on the Kentucky grid emits 5.1 times as much as one in California. US average 348 g/kWh. 62% of the signed load's power would come from fossil fuels, against 54% for the study's 403.
LG&E and KU (Kentucky)859 g/kWh
Arizona Public Service656 g/kWh
MISO (Midwest)445 g/kWh
Southwest Power Pool395 g/kWh
Southern Company (Georgia, Alabama)382 g/kWh
ERCOT (Texas)333 g/kWh
PJM (Mid-Atlantic, Ohio, Chicago)325 g/kWh
NV Energy320 g/kWh
Duke Energy Carolinas220 g/kWh
California ISO168 g/kWh
Data centers on the tracker, by the grid they are on
85% of the 1,965 data centers the tracker locates are on grids that get most of their power from fossil fuels. Largest 12 grids.
Mostly fossil fuelsMostly other sources
PJM (Mid-Atlantic, Ohio, Chicago)797
MISO (Midwest)152
ERCOT (Texas)134
California ISO110
Southwest Power Pool90
Southern Company (Georgia, Alabama)82
ISO New England80
New York ISO61
Salt River Project (Phoenix)45
Xcel Energy Colorado44
Portland General Electric41
Duke Energy Carolinas39
Where the AI campuses running today are
Each square is a campus, sized by CO2 a year. Squares were shifted to prevent overlaps. Orange: the grid serving it gets most of its power from fossil fuels.
CO2 a year from the AI campuses running today
Each rectangle is a campus, sized by CO2 at 58% of its power and grouped by state. Orange: the grid serving it gets most of its power from fossil fuels.
Mostly fossil fuelsMostly other sources
All 60 campuses
Anthropic-Amazon New Carlisle, Indiana: 1244 MW, 2.05 Mt
OpenAI Stargate Abilene, Texas: 1154 MW, 1.95 Mt
Colossus 2, Tennessee: 1276 MW, 1.89 Mt
Microsoft Fairwater Atlanta, Georgia: 859 MW, 1.67 Mt
Meta Prometheus, Ohio: 612 MW, 1.01 Mt
Microsoft Fairwater Wisconsin, Wisconsin: 442 MW, 1.00 Mt
Google Pryor (North), Oklahoma: 442 MW, 0.89 Mt
Meta Cheyenne, Wyoming: 182 MW, 0.78 Mt
Amazon Madison Mega Site, Mississippi: 341 MW, 0.77 Mt
Google New Albany, Ohio: 400 MW, 0.66 Mt
Google Council Bluffs (East), Iowa: 284 MW, 0.64 Mt
Colossus 1, Tennessee: 425 MW, 0.63 Mt
CoreWeave Denton TX, Texas: 367 MW, 0.62 Mt
Amazon Ridgeland, Mississippi: 273 MW, 0.62 Mt
Google Columbus, Ohio: 364 MW, 0.60 Mt
Meta Eagle Mountain, Utah: 179 MW, 0.58 Mt
Google Omaha, Nebraska: 284 MW, 0.57 Mt
Google Papillion, Nebraska: 284 MW, 0.57 Mt
QTS Richmond 1, Virginia: 333 MW, 0.55 Mt
Meta Rosemount, Minnesota: 241 MW, 0.55 Mt
Meta Jeffersonville, Indiana: 241 MW, 0.55 Mt
Microsoft Project Osmium, Iowa: 228 MW, 0.52 Mt
Google Bristow, Virginia: 286 MW, 0.47 Mt
Meta-QTS Hillsboro 2, Oregon: 243 MW, 0.45 Mt
AWS New Albany, Ohio: 255 MW, 0.42 Mt
QTS Richmond 2, Virginia: 252 MW, 0.42 Mt
Meta Temple, Texas: 231 MW, 0.39 Mt
Meta Montgomery, Alabama: 199 MW, 0.39 Mt
Google Storey County, Nevada: 214 MW, 0.35 Mt
Google Lincoln, Nebraska: 170 MW, 0.34 Mt
Coreweave Helios, Texas: 200 MW, 0.34 Mt
Microsoft Goodyear, Arizona: 263 MW, 0.33 Mt
QTS Richmond 3, Virginia: 202 MW, 0.33 Mt
Google Mesa, Arizona: 237 MW, 0.30 Mt
Meta Huntsville, Alabama: 198 MW, 0.29 Mt
Meta Aiken, S.C.: 168 MW, 0.29 Mt
Google Lancaster, Ohio: 164 MW, 0.27 Mt
Anthropic Lake Mariner, New York: 245 MW, 0.27 Mt
Google Kansas City East, Missouri: 126 MW, 0.25 Mt
Method: the one Guidi et al. use for the 403 largest data centers in Nature Sustainability (code and tables). Electricity is capacity × 8,760 hours × 58% load. CO2 is that electricity times the average CO2 per kWh of the grid serving it (EPA eGRID 2023). At 48% to 70% load the signed load would emit 225 to 328 Mt.
Today's grid is a placeholder: new gas plants built for this load would raise its CO2, new clean power would lower it. Like the study, the figures are location-based and do not net off companies' clean power contracts.
AI campuses: Epoch AI's estimates of each campus's facility power from satellite imagery, permits and filings, as of November 2026 (CC BY). Some, like xAI's Colossus campuses, also run on-site gas turbines, which a grid-average rate leaves out. Some were already among the study's 403. At 48% to 70% load the campuses would emit 23.6 to 34.4 Mt; 70% is the study's AI-heavy case.
Tracker data centers are the facilities on this site with a location, placed on their grid by coordinates. Fuel shares are the study's, from eGRID 2023. Grid demand for the Texas and California comparison is from EIA-930, May 2024 to April 2025.
The 403 largest data centers, 16 GW of capacity, are the study's verified hyperscale sites, May 2024 to April 2025. More have come online since. Countries' fossil CO2 is from Our World in Data's current release, 2024; some values differ from earlier releases.