6 Oracle datacenter sites across 3 states. 4 under construction, with $3.5M of construction value on the permits that disclose one.
| Operator / site | Location | Status | Construction value | Latest permit |
|---|---|---|---|---|
| Oracle | Austin, TX | Operational | $3.5M | 2018-10-29 |
| Oracle | Kansas City, MO | Under construction | ||
| Oracle | Kansas City, MO | Under construction | ||
| Oracle | Lees Summit, MO | Under construction | ||
| Oracle | Westminster, CO | Status unknown | ||
| Oracle | Broomfield, CO | Under construction |
We track 6 Oracle datacenter sites across 3 states, evidenced by building permits and public facility records. This counts sites we can tie to Oracle in public filings, so it is a floor rather than a complete corporate footprint: leased colocation space and sites permitted through unnamed LLCs may not be attributed here.
4 of the Oracle sites we track have permits indicating construction is under way, in Missouri, Colorado.
Digital Realty · Amazon / AWS · Equinix · DataBank · Flexential · Lumen · CoreSite · QTS Realty · CyrusOne · Microsoft · Centersquare · EdgeConneX · TierPoint · H5 Data Centers · Cogent · 365 Data Centers · VPLS · Vantage Data Centers · Crown Castle Inc. · ark data centers · Aligned Data Centers · T5 Data Centers · DartPoints, LLC · Expedient · Ziply Fiber · Netrality Data Centers · Iron Mountain Data Centers · Advanced Communications Technology · Stream Data Centers · Colocation America Corporation